Milestone 2 Exit Criteria
Features: (not comprehensive)
- First integration of Tango (not feature complete)
- MQ integration (not feature complete)
Reviews:
- One Pagers reviewed by community
- reviewed and approved by AS Architects
- Start user experience reviews
Bugs:
- No P1's.
- 50% reduction in P2s from the baseline. Any open P2's should be in a state 3 (evaluated) or higher. (The baseline is start of Milestone 2)
- 10% reduction in P3s per module from the baseline (by way of fixing, downgrading or closing).
- 40% of all P3's must be evaluated by the end of M2
- Forward port ALL P2 bugs from 8.2 branch
CTS:
- Run 1 combination of all tests - pass or don't pass. Will take 4 days.
Big Apps:
- Try a run for all Big Apps
- Need baseline numbers. No regression from AS9.0.
Documentation:
- Drafts of docs for features by 9/25/06.
- in pre-beta quality
- if engineering has not provided input, the feature may be thinly documented
- docs will only be reviewed for accuracy
This page (revision-3) was last changed on
12-Sep-06 17:18 PM, -0700
by Dhiru.
This page was created on
16-Aug-06 21:45 PM, -0700 by null.
More info...
| Version |
Date |
Author |
Size |
Changes ... |
|
3
|
12-Sep-06 17:18 PM, -0700
|
Dhiru |
1049 |
to previous
|
|
2
|
30-Aug-06 10:01 AM, -0700
|
Sridatta Viswanath |
963 |
to previous
|
to last
|
|
1
|
16-Aug-06 21:45 PM, -0700
|
unknown |
1056 |
to last
|