| Milestone | Target Date | Status | Feature list |
| 1 | Aug 14, 2006 | Released (Aug 16, 2006) | LB Admin, HADB Admin (internal), GF with Clustering, Enable new WS stack |
| 2 freeze | Sept 12, 2006 | Yet to Start | Tango, JBI integrated, Enable Profiles |
| 2 complete | Sept 26, 2006 | Yet to Start | No P1, No P2 (with exceptions), 10% reduction per module in P3s (bugster + issuetracker) (with exceptions). All onepagers reviewed and approved by appserver architects |
| 3 (feature complete) | Oct 31, 2006 | Yet to Start | Enable In-Memory Failover (early in the milestone), JSR196, ECC |
| 4 (Beta Release) | Dec 11, 2006 | Yet to Start | Feature Testing complete. No P1, P2 |
| 5 (FCS) | Apr 2007 | yet to start | All Testing Complete. No P1, P2, P3 |
Milestones (after M1) are intended to be stable enough to be useable and to elicit good feedback from the community. Other milestones may be added. The intention is to have about a milestone a month.